a)During the year 2012-2013 the work "Water supply to uncovered area of Barbil Muncipality (Ward No.2) has been completed. As a result 360 population are benefited by this project.
b)During the year 2012-2013 the work "Extension of PVC pipe to Sundara Basti & laying of new pipe line uncovered area of Barbil has been completed. As a result 570 population are benefited by this project.
c)During the year 2012-2013 the work "Replacement & installation of pump & motor including other electrical & M.S work raw water pump house at Barbil has been completed. As a result 740 population are benefited by this project.
d)During the year 2012-2013 the work "Protection of P.H Section office & P.H Staff Colony at Barbil has been completed. |
|
Joda Municipality under D. No. 13-4215 (State-Plan) |
a)During the year 2012-2013 the work "Extension of W/S to Ward No. 2 with production well & other ancillary works, Joda Muncipality has been completed. As a result 340 population are benefited by this project.
b)During the year 2012-2013 the work "Replacement of 350mm dia A.C pressure pipe by M.S/D.I/C.I pipe at Joda (Balance portion) has been completed. As a result 690 population are benefited by this project.
c)During the year 2012-2013 the work "Procurement & installation of pump & motor for Raw Water pump house & other ancillary work at Joda has been completed. As a result 1230 population are benefited by this project.
d)During the year 2012-2013 the work "Replacement of old pump set at clear water pump house at Joda has been completed. As a result 1230 population are benefited by this project.
e)During the year 2012-2013 the work "Replacement of 3" dia existing pipe by 4" dia & extension at Joda has been completed. As a result 630 population are benefited by this project. |
|
Anandapur Municipality under D. No. 13-4215 (State-Plan) |
During the year 2012-2013 the work "Installation Gas Chlorinator with construction of 2 Nos 5 lakhs litter capacity UGR near OHT with extension of pipe line to uncovered area of Anandapur Muncipality has been completed. As a result 1380 population are benefited by this project. |
|
Keonjhar Municipality under D. No. 13-4215 (State-Plan) |
a) During the year 2012-2013 the work "Improvement & provision of W/S to Keonjhar town has been completed. As a result 490 population are benefited by this project. |
|
Rajgangpur Municipality under D. No. 13-4215 (State-Plan) |
a) During the year 2012-2013 the work "Improvement of rising main of 200mm dia from Ranibandha to OCL gate - 1000 mtrs, Rajgangpur has been completed. As a result 9100 population are benefited by this project.
b)During the year 2012-2013 the work "W/S to uncovered area of Rajgangpur Muncipality has been completed. As a result 2000 population are benefited by this project.
c)During the year 2012-2013 the work "Sinking of 200 X 150mm deep bore well in Kansbahal for up-gradation of W/S to Panposh Census Town (Kanshabahal) has been completed. As a result 700 population are benefited by this project.
d)During the year 2012-2013 the work "Replacement of 75mm dia G.I pipe to 150mm dia C.I pipe - 550 mtrs in IT Colony, Rajgangpur has been completed. As a result 1000 population are benefited by this project.
e)During the year 2012-2013 the work "Sinking of 16 Nos hand pump tubewells in Rajgangpur Muncipality has been completed. As a result 2385 population are benefited by this project. |
|
Sundargarh Municipality under D. No. 13-4215 (State-Plan) |
a) During the year 2012-2013 the work "Water supply to uncovered Ward No. 8,11,12,13 & 16 of Sundargarh Municipality has been completed. As a result 1450 population are benefited by this project. |
|
Rourkela Municipality under D. No. 13-4215 (State-Plan) |
a) During the year 2012-2013 the work "Water supply to uncovered area of Chhend of Rourkela Municipality has been completed. As a result 1000 population are benefited by this project.
b) During the year 2012-2013 the work "Improvement of W/S to uncovered area of Ward No. 4,32,33 etc. of Rourkela Municipality has been completed. As a result 1540 population are benefited by this project. |
|
Biramitrapur Municipality under D.No. 13-4215 (State-plan). |
a)During the year 2012-2013 the work Improvement of W/S to uncovered area of Biramitrapur has been completed. As a result 500 population are benefited by this project.
b)During the year 2012-2013 the work "Improvement of source & intake arrangement including replacement of pump set has been completed. As a result 500 population are benefited by this project.
c)During the year 2012-2013 the work "Sinking of 26 Nos. hand pump tubewells in Biramitrapur Muncipality has been completed. As a result 3900 population are benefited by this project. |
|
AUTOMATION OF WATER TREATMENT PLANTS AT PALASUNI, BHUBANESWAR. |
PHEO, Bhubaneswar has successfully implemented the project for automation of water treatment plants at Palasuni, Bhubaneswar. |
autamation ofPalasuni water plant pdf.pdf |